This project involved a complete strip out of the existing college boiler room and the installation of two new heating boilers, two new gas fired hot water heaters and all associated plant & controls.
The works took place during the summer shut down and a challenging programme was made even more so by the presence of asbestos. However following specialist removal we were able to complete and commission all services in time for the pupils’ return for the autumn term.